The No. 3 Unit of CNEEC-contracted Laos HONGSA 3x626MW power plant project underwent the performance test in early January and passed the 30-day continuous reliability commissioning test at one time on February 15, 2016. Moreover, CNEEC assisted the owner in completing the power system stability test with combined operation of 3 units. The unit underwent the 100-hour continuous reliability test on February 25 and was handed over to the owner and entered its warranty period on March 1. The owner also entered the stage of commercial operation at 0:00 on March 2 as scheduled.

The successful handover of Unit 3 marks that the CNEEC-contracted project has entered the warranty phase. The project office promises to continue to complete all its tasks during the warranty phase.

CMEC - China Machinery Engineering Corporation issued this content on 03 March 2016 and is solely responsible for the information contained herein. Distributed by Public, unedited and unaltered, on 22 March 2016 08:28:13 UTC